Permits Push Gigawatts of Data Centers From 2027 Into 2028

Builders have workers and equipment, SemiAnalysis says, but they cannot get approvals to proceed.

AI image
Sourcery with Molly O'Shea · Dylan Patel, SemiAnalysis

SemiAnalysis founder Dylan Patel says his firm has moved multiple gigawatts of planned data-center capacity out of 2027 and into 2028 because the permits are not available. A gigawatt is a billion watts of electrical power, enough for very large computing projects.

That delay matters because it pushes back when new computing power becomes usable, even though builders are otherwise ready to build.

The holdup is not labor or equipment, according to Patel. His firm monitors data-center projects worldwide and their timelines, and it expects more delays in 2028 for the same reason.

In Texas, Governor Hinojosa has said publicly that she will not stop data centers, Patel says. She said she will make sure they do not raise electricity prices, use water responsibly, and address union labor.

State officials can use water, wastewater, stormwater, and air permits to stop projects, Patel says. Even a project that uses little water and is not connected to the grid could be stopped through an air permit.

How strictly Texas applies those rules, especially on labor, remains to be seen. Patel questioned how the state would require union labor when it has little union labor, noting that electricians and industrial plumbers on these projects can earn $200,000 or more.

More places beyond Texas are imposing bans or pauses, but most have little or no existing capacity, Patel says. He added that additional gigawatts now planned for 2028 are also at risk of slipping.

Questions people ask

How much power is a gigawatt?

A gigawatt is one billion watts of electrical capacity. In data centers, it describes how much power the buildings are designed to draw to run servers and cooling. Multiple gigawatts is enough to cover several very large data-center projects.

Why would a data center need water or air permits if it uses little water?

Data centers can need several permits even if daily water use is low. Construction can disturb stormwater runoff, cooling and bathrooms create wastewater, and local agencies often require proof that water supplies will remain adequate. An air permit can separately cover backup generators and other emissions.

Can a state really block a project over an air permit?

Yes. States generally administer air permits under federal clean air rules and can deny or delay them. Without an approved permit, a project cannot legally build or operate equipment that emits regulated pollutants, including backup power systems.